Location: Caldwell, Ohio
Purpose/Opportunity:
A client approached us to handle the construction of their booster station, which had a tight schedule for critical path items and mechanical completion.
Methods:
We mobilized a construction team of 30 craftsmen to the site and utilized our resources to bring in an additional 20 craftsmen, ensuring the client met their critical path date and mechanical completion within the requested time frame.
Results/Benefits:
We effectively provided manpower as needed to meet critical deadlines. The work was completed safely and promptly, finishing on time with no safety incidents or recordable issues. Our client received the high standard of buildability that Strike is known for. The project included the installation of 4 compressors, 4 tanks, a compressor discharge filter/coalescer, a glycol contractor, a TEG filter separator, an inlet slug catcher, a BTEX unit, and generator hookups/installs. We laid 14,000 LF of piping, completed 8,000 weld inches, and installed 400 pipe supports, all within 54,652 manhours.