Cathodic Protection – Groundbed Installation

Location: Houston, Texas, USA

Purpose/Opportunity:

The client approached us having pipe to soil data that did not meet PHMSA criteria. The project was faced with the challenge of installing groundbeds in restrictive areas.

Methods:

We installed the groundbeds in restricted sites like residential yards and prison properties. Our crew was sure to keep a clean job site and leave a clean location when the project was wrapped up.

Results/Benefits:

Our team consisted of 2 crew members, 2 subcontract drill crew members, and the project was completed in 8 days. The project was completed within schedule and budget.