Gas Processing Plant in Midland County, Texas
We are excited to share the completion of a new gas processing plant located in Midland County, Texas. This facility was designed to process 250 million standard cubic feet per day (MMSCFD) of natural gas, comprised of Intermediate Pressure (IP) Compression, Slug Catcher, Amine System, Residue Compression, Flare, Instrument Air System. Our most recent scope of work on this facility included erection of 68 tons of structural steel, completion of 45,000 weld inches, installation of 27,822 linear feet of pipe, and 50 pneumatic pressure tests.
The project involved the installation of:
- 27,822 Linear Feet of Pipe
- 45,000 Weld Inches
- 68 Tons of Structural Steel